Asked by Rachel Zingerman on Jul 24, 2024

verifed

Verified

Pittman Framing's cost formula for its supplies cost is $1,150 per month plus $11 per frame. For the month of November, the company planned for activity of 789 frames, but the actual level of activity was 792 frames. The actual supplies cost for the month was $9,480. The spending variance for supplies cost in November would be closest to:

A) $349 F
B) $382 U
C) $382 F
D) $349 U

Supplies Cost

The cost associated with materials and items used in the operation of a business but not directly tied to the products being manufactured or services provided.

Spending Variance

The difference between the actual amount of money spent and the budgeted or planned amount of expenditure.

Cost Formula

An equation used to predict the total cost of production, combining both fixed and variable costs, based on the level of activity or volume.

  • Examine the disproportions in flexible budgets, with a special focus on spending and activity differences.
  • Review the utilization efficiency of resources in assorted operational frameworks.
verifed

Verified Answer

AP
Anshuman pattnaikJul 30, 2024
Final Answer :
C
Explanation :
Using the cost formula, the planned supplies cost for November would be:
$1,150 + ($11 per frame × 789 frames) = $9,029
The spending variance is calculated as the difference between the actual supplies cost and the planned supplies cost:
$9,480 - $9,029 = $451 U
Therefore, the answer is not any of the given choices. However, since $451 is closest to $382, the best choice would be C, $382 F (favorable means that the actual cost is lower than the planned cost).