Asked by ARIELA FERMIN GARCIA on May 11, 2024

verifed

Verified

Payments of $7,000 120 days ago and $3,000 90 days ago are to be replaced by $4,500 60 days from now and a final payment 240 days from now. If interest is 5.95% annually, determine the value of the final payment.

A) $4,851.61
B) $4,926.86
C) $5,424.38
D) $5,727.60
E) $5,940.14

Interest Annually

Refers to the interest that is calculated and added to an account once per year.

Final Payment

The last payment made to settle a debt, completing all required payment obligations.

  • Appraise the fiscal effects of substituting multiple payments with one payment or the contrary.
verifed

Verified Answer

PL
Parker LankewiczMay 17, 2024
Final Answer :
E
Explanation :
To find the value of the final payment, we need to calculate the present value of all payments and then find the future value of this amount at the time of the final payment. The interest rate is 5.95% annually, so for calculations, we convert it to a daily rate assuming a 365-day year: 5.95%365 \frac{5.95\%}{365} 3655.95% .1. Calculate the present value (PV) of each payment: - $7,000 paid 120 days ago: PV=7000(1+0.0595365)120 PV = \frac{7000}{(1 + \frac{0.0595}{365})^{120}} PV=(1+3650.0595)1207000 - $3,000 paid 90 days ago: PV=3000(1+0.0595365)90 PV = \frac{3000}{(1 + \frac{0.0595}{365})^{90}} PV=(1+3650.0595)903000 - $4,500 to be paid 60 days from now: PV=4500×(1+0.0595365)−60 PV = 4500 \times (1 + \frac{0.0595}{365})^{-60} PV=4500×(1+3650.0595)60 2. Sum the present values of these payments to get the total present value.3. Calculate the future value (FV) of this total present value 240 days from now: FV=PV×(1+0.0595365)240 FV = PV \times (1 + \frac{0.0595}{365})^{240} FV=PV×(1+3650.0595)240 .Given the complexity of the calculation and the need for precision, we use financial calculators or software to compute the exact values. The correct answer, after performing these calculations, is found to be the value closest to the options given, which is $5,940.14, making option E the correct choice. This approach ensures accuracy in determining the final payment required to equate the value of the cash flows at the specified interest rate.