Asked by ashanti morris on May 10, 2024

verifed

Verified

Normal Projects Q and R have the same NPV when the discount rate is zero.However,Project Q's cash flows come in faster than those of R.Therefore,we know that at any discount rate greater than zero,R will have a higher NPV than Q.

Discount Rate

The discount rate employed to ascertain the present worth of forthcoming cash flows in an analysis of discounted cash flow.

NPV

Net Present Value; the calculation of the present value of cash inflows minus the present value of cash outflows over a period.

Cash Flows

The movement of money into and out of a business, representing its operating, investing, and financing activities.

  • Analyze the relationship between project cash flow timing and project evaluation metrics.
verifed

Verified Answer

EK
Emmet Keeffe IVMay 16, 2024
Final Answer :
False
Explanation :
The statement is incorrect. If Q's cash flows are coming in faster, it means that Q has a shorter payback period and a higher internal rate of return (IRR) than R. Therefore, at discount rates lower than IRR, Q will have a higher NPV than R. However, at discount rates higher than IRR, R will have a higher NPV than Q. It cannot be concluded that R will always have a higher NPV than Q at any discount rate greater than zero without additional information about their respective IRRs.