Lavoie Company planned to use 18,500 pounds of material costing $2.50 per pound to make 4,000 units of its product.In actually making 4,000 units,the company used 18,800 pounds that cost $2.54 per pound.Calculate the direct materials quantity variance.

Direct Materials Quantity Variance

The difference between the actual amount of materials used in production and the expected amount.

Pounds

A unit of weight commonly used in the British imperial and United States customary systems, equivalent to 0.453592 kilograms.

  • Familiarize oneself with the techniques for determining various variances, encompassing material, labor, and overhead.
verifed

Verified Answer

MM
Megan McCurdyMay 18, 2024
Final Answer :