In which of these scenarios is a more detailed work plan most appropriate?

A) A short report that needs to be prepared and mailed in a day
B) An informal report providing feedback about the new coffee machine in the office
C) An automated report generated by a software that analyzes data
D) A report involving collaboration between three teams, which are based in different cities

Detailed Work Plan

A comprehensive document outlining the tasks, timelines, resources, and milestones for completing a specific project or work package.

Automated Report

A document generated automatically through software, summarizing data or outcomes without manual intervention.

  • Recognize the intent and categories of business reports, and their essential contribution to decision-making activities in organizations.
verifed

Verified Answer

ZK
Zybrea KnightMay 03, 2024
Final Answer :
D
Explanation :
A more detailed work plan is most appropriate for a report involving collaboration between three teams based in different cities to ensure that everyone is on the same page, timelines are synchronized, and responsibilities are clear. A detailed work plan may not be necessary for the other scenarios.