Asked by Sophia Winner on Jun 03, 2024

verifed

Verified

In the PDCA cycle, what does "P" stand for?

A) Priorities
B) Procedures
C) Personnel
D) Plan
E) Productivity

Priorities

The importance, ranking, or urgency assigned to tasks or projects, determining the order in which they should be addressed.

Procedures

Established methods or protocols followed in order to accomplish tasks or operations consistently and efficiently.

Personnel

Refers to the employees or staff of an organization, often used interchangeably with "human resources" to denote the workforce component.

  • Comprehend and utilize the PDCA cycle in perpetual improvement methodologies.
verifed

Verified Answer

ZK
Zybrea KnightJun 03, 2024
Final Answer :
D
Explanation :
"P" in the PDCA cycle stands for Plan, which involves defining the problem, setting objectives, and developing strategies and action plans to achieve those objectives.