If we are to use Solver to determine where the new plant has to be built,what is the amount shipped from Kansas to Memphis?

A) 0 units
B) 3,000 units
C) 200 units
D) 1,000 units

Double-subscripted Variables

variables in mathematics and programming denoted with two subscripts, usually to represent matrix elements or the interaction between two dimensions.

Binary Variable

A binary variable is a type of variable that can take one of two possible values, typically represented as 0 or 1, to indicate the absence or presence of some characteristic.

  • Compute ideal quantities for shipping to reduce transportation expenses.
verifed

Verified Answer

AE
Ashle ElizabethJul 16, 2024
Final Answer :
B
Explanation :
To determine which plant to build, we need to maximize the total demand that can be met while minimizing the transportation cost. We can use the Xij variables and the Y1 and Y2 binary variables to formulate the problem as a linear programming problem. After solving the problem with Solver, we get that the amount shipped from Kansas to Memphis is 3,000 units. The objective function value is $43,000, which is the minimum transportation cost. Therefore, the best choice is to build the Kansas plant.