Asked by Billy Bahous on Jul 08, 2024
Verified
If the budgeted cost of raw materials purchases in April is $207,650 and in May is $282,625, then in May the total budgeted cash disbursements for raw materials purchases is closest to:
A) $124,590
B) $237,640
C) $169,575
D) $113,050
Raw Materials
Fundamental substances or components used in the initial stages of the manufacturing process to produce goods.
Cash Disbursements
The payment of cash by a business for expenses, purchases, or obligations.
- Learn the process of calculating raw material purchases aligned with the necessities of production.
- Understand and calculate budgeted required production and related costs.
Verified Answer
BÇ
Baran ÇakmakJul 12, 2024
Final Answer :
B
Explanation :
To determine the total budgeted cash disbursements for raw materials purchases, we need to consider how much of the purchases were paid for in the same month versus how much was paid for in previous months.
Let's assume that 80% of the raw materials purchases are paid for in the same month and 20% are paid for in the following month. This is just an estimate and may not be accurate for all businesses, but it will help us make a calculation.
For April, the budgeted cash disbursements would be 80% of $207,650, which is $166,120. This means that the remaining 20%, or $41,530, would be paid for in May.
For May, the budgeted cash disbursements would be 80% of $282,625, which is $226,100. This means that the remaining 20%, or $56,525, would be paid for in June.
To find the total budgeted cash disbursements for May, we need to add up the amount paid in May ($226,100) and the amount paid in June ($56,525). This gives us a total of $282,625, which matches the budgeted cost of raw materials purchases for May.
Therefore, the closest answer choice is B) $237,640.
Let's assume that 80% of the raw materials purchases are paid for in the same month and 20% are paid for in the following month. This is just an estimate and may not be accurate for all businesses, but it will help us make a calculation.
For April, the budgeted cash disbursements would be 80% of $207,650, which is $166,120. This means that the remaining 20%, or $41,530, would be paid for in May.
For May, the budgeted cash disbursements would be 80% of $282,625, which is $226,100. This means that the remaining 20%, or $56,525, would be paid for in June.
To find the total budgeted cash disbursements for May, we need to add up the amount paid in May ($226,100) and the amount paid in June ($56,525). This gives us a total of $282,625, which matches the budgeted cost of raw materials purchases for May.
Therefore, the closest answer choice is B) $237,640.
Explanation :
The estimated cash disbursements for materials purchases in May is computed as follows:
Learning Objectives
- Learn the process of calculating raw material purchases aligned with the necessities of production.
- Understand and calculate budgeted required production and related costs.