Asked by Veronica Vaselin on May 06, 2024

verifed

Verified

Hubbard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During January, the kennel budgeted for 2,100 tenant-days, but its actual level of activity was 2,060 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for January:Data used in budgeting: Hubbard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During January, the kennel budgeted for 2,100 tenant-days, but its actual level of activity was 2,060 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for January:Data used in budgeting:   Actual results for January:   The wages and salaries in the planning budget for January would be closest to: A)  $17,282 B)  $17,618 C)  $17,420 D)  $17,132 Actual results for January:
Hubbard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During January, the kennel budgeted for 2,100 tenant-days, but its actual level of activity was 2,060 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for January:Data used in budgeting:   Actual results for January:   The wages and salaries in the planning budget for January would be closest to: A)  $17,282 B)  $17,618 C)  $17,420 D)  $17,132 The wages and salaries in the planning budget for January would be closest to:

A) $17,282
B) $17,618
C) $17,420
D) $17,132

Tenant-Days

A metric in property management, indicating the total number of days that units were occupied by tenants within a specific period.

Wages and Salaries

Payments to employees for their work or services, typically on an hourly (wages) or annual (salaries) basis.

Planning Budget

A forward-looking budget that outlines the financial plans, objectives, and resources over a specific timeframe, often used for guiding the operations and evaluating performance.

  • Apply dynamic financial estimating methods to gauge forecasted costs in accordance with established activity benchmarks.
  • Analyze the outcome of changes in operational intensity on budget formulations.
  • Understand the role of fixed and variable costs in budgeting and variance analysis.
verifed

Verified Answer

LN
Lening NunezMay 12, 2024
Final Answer :
C
Explanation :
First, we need to find the variable cost per tenant-day. According to the given data:

Variable cost per tenant-day = Budgeted variable costs ÷ Budgeted tenant-days = $12,210 ÷ 2,100 = $5.81 per tenant-day

Using this variable cost per tenant-day, we can calculate the flexible budget for actual activity level:

Flexible budget = Variable cost per tenant-day x Actual tenant-days = $5.81 x 2,060 = $11,967.60

Now, we can calculate the total wages and salaries for January:

Total wages and salaries = Fixed costs + Variable cost per tenant-day x Actual tenant-days
= $5,480 + $5.81 x 2,060
= $17,419.60

Therefore, the closest option is C) $17,420.