Asked by Dheandra Armyra on Jul 29, 2024

verifed

Verified

Given the following data:  Present investment required $12,000 Net present value $430 Annual cost savings $? Discount rate 12% Life of the project 10 years \begin{array} { | l | l | } \hline \text { Present investment required } & \$ 12,000 \\\hline \text { Net present value } & \$ 430 \\\hline \text { Annual cost savings } & \$ ? \\\hline \text { Discount rate } & 12 \% \\\hline \text { Life of the project } & 10 \text { years } \\\hline\end{array} Present investment required  Net present value  Annual cost savings  Discount rate  Life of the project $12,000$430$?12%10 years  Based on the data given, the annual cost savings would be:

A) $2,123.89.
B) $2,200.00.
C) $1,630.00.
D) $2,553.89.

Discount Rate

This is the discount rate used in the process of discounted cash flow analysis to find out the current value of cash flows expected in the future.

Annual Cost Savings

The reduction in costs achieved during a fiscal year, often as a result of process improvements or cost-cutting measures.

Net Present Value

The difference between the present value of cash inflows and the present value of cash outflows, used in capital budgeting to assess the profitability of an investment or project.

  • Achieve expertise in applying the concept of net present value (NPV) to investment considerations.
verifed

Verified Answer

AA
alexia allenAug 04, 2024
Final Answer :
B
Explanation :
The annual cost savings can be calculated using the formula for the present value of an annuity because the net present value (NPV) is given, and we are asked to find the annual cost savings, which can be considered as an annuity. The formula to use is: NPV=P×(1−(1+r)−nr)NPV = P \times \left(\frac{1 - (1 + r)^{-n}}{r}\right)NPV=P×(r1(1+r)n) where PPP is the annual payment (annual cost savings in this case), rrr is the discount rate, and nnn is the number of periods. Rearranging the formula to solve for PPP gives: P=NPV(1−(1+r)−nr)P = \frac{NPV}{\left(\frac{1 - (1 + r)^{-n}}{r}\right)}P=(r1(1+r)n)NPV Given that NPV=$430NPV = \$430NPV=$430 , r=12%=0.12r = 12\% = 0.12r=12%=0.12 , and n=10n = 10n=10 years, we can substitute these values into the formula: P=430(1−(1+0.12)−100.12)P = \frac{430}{\left(\frac{1 - (1 + 0.12)^{-10}}{0.12}\right)}P=(0.121(1+0.12)10)430 Calculating the denominator: 1−(1+0.12)−100.12≈5.6502\frac{1 - (1 + 0.12)^{-10}}{0.12} \approx 5.65020.121(1+0.12)105.6502 Then, calculating PPP : P=4305.6502≈76.12P = \frac{430}{5.6502} \approx 76.12P=5.650243076.12 However, this calculation does not directly lead to any of the provided options, indicating a misunderstanding in the application of the formula or the interpretation of the question. The correct approach involves understanding the incremental cost approach and the specifics of the capital budgeting analysis, which might not directly apply the given formula in this context. The correct answer, based on the options provided and considering the typical approach to finding annual cost savings using NPV and other given data, seems to have been misunderstood in this explanation. The correct calculation should relate to the difference in cash flows between the two machines, considering their operating costs, overhaul costs, and salvage values, not the unrelated project data provided in the second table. Therefore, the explanation provided does not accurately solve the given problem, and a reevaluation of the problem statement and the correct application of capital budgeting principles is necessary to find the annual cost savings.