Boursaw Corporation has provided the following data concerning last month's operations. Boursaw Corporation has provided the following data concerning last month's operations.   Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. How much is the total manufacturing cost for the month on the Schedule of Cost of Goods Manufactured? A)  $144,000 B)  $160,000 C)  $216,000 D)  $164,000 Any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold.
How much is the total manufacturing cost for the month on the Schedule of Cost of Goods Manufactured?

A) $144,000
B) $160,000
C) $216,000
D) $164,000

Total Manufacturing Cost

The aggregate of all costs—direct materials, direct labor, and manufacturing overhead—incurred in producing finished goods.

  • Compute the expense involved in the production of goods.
verifed

Verified Answer

DV
Desiree VarelaJun 20, 2024
Final Answer :
B
Explanation :
Total manufacturing cost for the month can be calculated as:
Direct materials used + Direct labor + Manufacturing overhead applied
= $56,000 + $40,000 + $64,000
= $160,000