Because problems with fixed-position layouts are so difficult to solve well onsite, operations managers

A) virtually never employ this layout strategy.
B) utilize this approach only for construction projects such as bridges and office towers.
C) increase the size of the site.
D) often complete as much of the project as possible off-site.
E) utilize this layout only for defence contractors.

Fixed-position Layouts

A type of industrial layout where the product remains stationary, and equipment, labor, and components are moved as needed to the product's location for assembly or construction.

Off-site

Off-site refers to activities or processes that are conducted away from the primary location or site, often implying external premises.

  • Differentiate among layout types based on operational specifics.
  • Investigate novel strategies for organizing the workplace.
verifed

Verified Answer

VR
Veronica RodriguezJun 02, 2024
Final Answer :
D
Explanation :
Fixed-position layouts are often used for large projects such as ships, aircraft, and buildings. However, due to the difficulties of managing resources and coordinating activities onsite, operations managers often complete as much of the project as possible off-site in order to reduce the amount of work that needs to be done in the fixed position. This can help to reduce costs and improve efficiency.