Asked by theresa betty on Jun 03, 2024
Verified
After looking at the PERT chart for the development of the new fashion line,Quinn realized that the longest path showed that the project would take a minimum of 60 days.Quinn was able to get this information as a result of the:
A) longest path method.
B) activity path method.
C) critical path method.
D) project path method.
Critical Path Method
A project management technique for determining the longest sequence of dependent tasks and scheduling resources to optimize achievement of project objectives.
PERT Chart
A project management tool used to schedule, organize, and coordinate tasks within a project, standing for Program Evaluation and Review Technique.
Longest Path
In project management, the sequence of tasks that determines the minimum timeframe required to complete a project, with any delay in these tasks delaying the whole project.
- Strengthen abilities in formulating and scrutinizing Gantt and PERT charts.
Verified Answer
Learning Objectives
- Strengthen abilities in formulating and scrutinizing Gantt and PERT charts.
Related questions
Which of the Following Is Applicable to 'PERT ...
The _____ Is a Project Management Tool That Describes the ...
In Order to Track Their Progress,Sharon's Team Developed a Chart ...
A Project Management Tool That Helps Identify Sequences of Dependent ...
Develop a PERT Chart for a Team Project for Work ...