Asked by theresa betty on Jun 03, 2024

verifed

Verified

After looking at the PERT chart for the development of the new fashion line,Quinn realized that the longest path showed that the project would take a minimum of 60 days.Quinn was able to get this information as a result of the:

A) longest path method.
B) activity path method.
C) critical path method.
D) project path method.

Critical Path Method

A project management technique for determining the longest sequence of dependent tasks and scheduling resources to optimize achievement of project objectives.

PERT Chart

A project management tool used to schedule, organize, and coordinate tasks within a project, standing for Program Evaluation and Review Technique.

Longest Path

In project management, the sequence of tasks that determines the minimum timeframe required to complete a project, with any delay in these tasks delaying the whole project.

  • Strengthen abilities in formulating and scrutinizing Gantt and PERT charts.
verifed

Verified Answer

SA
Sarah AlbannawJun 06, 2024
Final Answer :
C
Explanation :
The critical path method is a project management technique that identifies the critical path, which is the sequence of activities that determine the shortest possible duration of a project. The longest path on the PERT chart is the critical path, and it represents the minimum amount of time required to complete the project. Therefore, Quinn was able to determine the minimum duration of the project using the critical path method.