Asked by Jasmine Agosto on May 26, 2024
Verified
A production process using two inputs, labor and capital, can be written as:
Q = 5LK MPK = 5L MPL = 5K
where Q represents output per day (tons). The unit costs of inputs are $150 for labor (L) and $1,000 for capital (K). Determine the least cost combination of L and K when output is produced at the rate of 1,000 tons per day. Determine the required outlay for 1,000 tons per day.
Least Cost Combination
An economic principle where firms seek to minimize production costs by using the most efficient combination of resources.
Inputs
The resources used in the production process, such as labor, raw materials, and capital equipment.
Output Per Day
The total quantity of goods or services produced by an entity in a single day.
- Identify the most favorable input combinations in light of a production function and budgetary constraints.
Verified Answer
SB
Suraj BudhaprithiMay 26, 2024
Final Answer :
The least cost combination of inputs occurs where the ratio of prices of inputs equals the marginal rate of technical substitution of one input for another.
The price ratio is PL/PK = 150/1,000 = 0.15.
Now find the combination of L and K that will make MRTS equal to 0.15.
MRTS = = = 0.15
K = 0.15L
The output rate is 1000 = Q, thus
1000 = 5LK = 5L(0.15L) = 0.75L2
L = = 36.51 units.
K = 0.15(36.51) = 5.48 units.
The total outlay needed to purchase inputs to satisfy this production rate is:
I = PLL + PKK
I = 150(36.51) + 1,000(5.48)
= $5,476.50 + 5,480
I = $10,956.50 total outlay per day.
The price ratio is PL/PK = 150/1,000 = 0.15.
Now find the combination of L and K that will make MRTS equal to 0.15.
MRTS = = = 0.15
K = 0.15L
The output rate is 1000 = Q, thus
1000 = 5LK = 5L(0.15L) = 0.75L2
L = = 36.51 units.
K = 0.15(36.51) = 5.48 units.
The total outlay needed to purchase inputs to satisfy this production rate is:
I = PLL + PKK
I = 150(36.51) + 1,000(5.48)
= $5,476.50 + 5,480
I = $10,956.50 total outlay per day.
Learning Objectives
- Identify the most favorable input combinations in light of a production function and budgetary constraints.